The process of reinforcing the corners of the towers and replacing the conductors of Al Omayed / El Alamin line with 66 KV with heat conductors and the installation of rubber insulation chains

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egyptian Electricity Transmission Company
Country: Egypt
Duration: 60 days
Execution Period: Under construction
Year of Contract: 2018

HDD for interconnection cables 220 KV between Imbaba Station and Meatmedya station

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: 4.5 months
Execution Period: Under construction
Year of Contract: 2018

HDD for interconnection Saqer Qouraish Station, Gardenia and The Airport

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: 3 months
Execution Period: Under construction
Year of Contract: 2018

Construction of 66 KV double-circuit cable, type XLPE strip (1 x 400 mm 2), to connect with The North Ismailia Station

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egyptian Electricity Transmission Company
Country: Egypt
Duration: month
Execution Period: month
Year of Contract: 2018
Noth ismalia

Al Obour City 1 Crossing

Project Owner: Egyptian Electricity Transmission Company
Client Name: EAl Namaa
Country: Egypt
Duration: 2 Weeks
Execution Period: 10 days
Year of Contract: 2018

Al Obour City 2 Crossing

Project Owner: Egyptian Electricity Transmission Company
Client Name: EAl Namaa
Country: Egypt
Duration: 2 Weeks
Execution Period: 10 days
Year of Contract: 2018

2017

HDD for construction lines and provision cables 220 KV. and set the overhead lines (Al Shorouq City) 66 KV.

Project Owner: Egyptian Electricity Transmission Company
Client Name: Giza Misr
Country: Egypt
Duration: Month
Execution Period: 10 days
Year of Contract: 2017

Connect Al Marg Generator Station with the new Takreer Petrol Generator Station 66 KV. Cables (Mustorod)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2017

Installing process 66 KV cables, type XLPE strip (1 x 400 mm2), copper covered by lead, and full fiber cables with accessories to set the 1st Settlement 66 KV with double circle ground cables, strip (1 x 400 mm2), 3.5 m. length

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egypt Cables
Country: Egypt
Duration: 3 months
Execution Period: Under construction
Year of Contract: 2017

2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(Ghataty stage No. 26)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(Al Terssa stage No. 4)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(Mashaal stage No. 6)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 6)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 9 days
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 10)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 11)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 11 days
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 13)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 11 days
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 15)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: Week
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 17)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 15 days
Year of Contract: 2016

Connect Al Hadaba Generator Station with Cairo Generator Station 500
(stage No. 23)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: Week
Year of Contract: 2016

Crossing Sherweeda railway, Al Canal Electricity Station ( El-Zaggazig)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egyptian Company For Construction & Investments
Country: Egypt
Duration: Month
Execution Period: 21 days
Year of Contract: 2016

Connect West Cairo Generating Station with Imbaba Generator Station,
220 KV cables (Al Manashy)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: Month
Execution Period: 28 days
Year of Contract: 2016

Connecting project Ramses Metro Station / Al Abbasya Metro Station
(Al Sekka Al Baydaa)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 2 months
Year of Contract: 2016

HDD to connect two electricity stations 66 KV double circle in El Marg Area in the bottom of the subway

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables
Country: Egypt
Duration: 21 days
Execution Period: Month
Year of Contract: 2016

Connecting project Ramses Metro Station / Al Abbasya Metro Station
(Al Sekka Al Baydaa)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: 2 months
Year of Contract: 2016

Connecting project Ramses Metro Station / Al Abbasya Metro Station
(Salah Salem)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables
Country: Egypt
Duration: Month
Execution Period: Month
Year of Contract: 2016

HDD for interconnection MV cables 66 KV between El-Maasara s\s and New Assuit s\s. (Canal)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egyptian Company For Construction & Investments
Country: Egypt
Duration: Month
Execution Period: 15 days
Year of Contract: 2016

HDD for interconnection MV cables 66 KV between El-Maasara s\s and New Assuit s\s. (Nile)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egyptian Company For Construction & Investments
Country: Egypt
Duration: 2 months
Execution Period: 3 months
Year of Contract: 2016

HDD for interconnection MV cables 220 KV between west of Cairo S/S to new Imbaba S\S, route length 220 m (El- Koum El-Ahmer)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 16 days
Execution Period: Week
Year of Contract: 2016

HDD for interconnection MV cables 220 KV between west of Cairo S/S to new Imbaba S\S, route length 144 m (the ring regional)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 16 days
Execution Period: Week
Year of Contract: 2016

HDD for interconnection MV cables 220 KV between west of Cairo S/S to new Imbaba S\S, route length 200 m (Bashteel)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 16 days
Execution Period: 5 days
Year of Contract: 2016

HDD for interconnection MV between Maadi S/S to El-Sakaken under Zahraa
El-Maadi Tunnel S\S

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 3 months
Execution Period: 2 months
Year of Contract: 2016

HDD for interconnection MV between El-Koraymat keys S/S to El-Basateen In Cairo under the railway

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 45 days
Execution Period: 30 days
Year of Contract: 2016

HDD for interconnection MV between El-Koraymat keys S/S to El-Basateen In Cairo under the Autostorad road under the ring road

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 60 days
Execution Period: 45 days
Year of Contract: 2016

2015

Crossing by HDD in the Ring Road for interconnection between Sharm El- Sheikh (220 KV) to Sharm El-Sheikh generator cables (220 KV) & 8 inch pipe and 2 pipes for the Viper Optics Cables (8 Crossing)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Energya Cables Company
Country: Egypt
Duration: 1 month
Execution Period: 15 days
Year of Contract: 2015

Crossing by HDD in Hurghada, for 220 KV 12 pipes each 8 inch & 2 pipes each 4 inch (14 Crossing)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 45 days
Execution Period: 22 days
Year of Contract: 2015

CHDD for interconnection MV cables 500 KV at West of Assuit S/S stage (1)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 45 days
Execution Period: 15 days
Year of Contract: 2015

HDD for interconnection MV cables 500 KV at West of Assuit S/S stage (2)

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 45 days
Execution Period: 15 days
Year of Contract: 2015

2013

HDD under Abd El-Hamid Badawy Road (Airport), for number of 7 HDPE pipe, each 10 Inches, Route Length 220 linear m.

Project Owner: Egyptian Electricity Transmission Company
Client Name: Egy-Tech Cables Egypt
Country: Egypt
Duration: 2 months
Execution Period: 15 days
Year of Contract: 2013

2010

HDD under Autostrad Road for Abbasiya Metro project, for number of 7 HDPE pipe, each 10 Inches, Route Length 220 linear m.

Project Owner: Egyptian-French Company for Tunneling & Egyptian Electricity Transmission Company
Client Name: Giza Cables Company
Country: Egypt
Duration: 3 months
Execution Period: 1.5 months
Year of Contract: 2010